MELBOURNE (Indonesia Today) – MEO Australia Limited anticipates that drilling of Gurame SE-1X in Seruway block will commence in early October.
The drilling will take 35 days to complete on an untested basis or 50 days in the likely event it is production tested, Jurgen Hendrich, managing director and CEO of MEO Australia Limited said this morning.
Seruway Offshore Exploration Limited (SOEL), subsidiary of MEO Australia, has agreed to execute a binding agreement with Zaratex NV (Zaratex) and Hercules Offshore Inc (Hercules) to secure the second of Zaratex