JAKARTA (Yosefardi) – Jakarta governor Joko ‘Jokowi’ Widodo insisted that he would only make decision on the construction of six toll roads in Jakarta after mass rapid transit (MRT) system.
The PDI-P politician said there are several options for the toll roads. “Be patient, we’re calculating everything,” he said Friday.
Construction of the six toll road projects (69.77 KM in total length) will be divided into four stages. First stage consists of Semanan-Sunter (20 KM) with Rp9.76 trillion of investment and Sunter-Pulo Gebang (9.44 KM) for Rp7.37 trillion.
Phase Two consists of Duri – Pulo Gebang (12.65 KM) with Rp5.96 trillion of investments and Kemayoran – Kampung Melayu (9.6 KM) for Rp6.95 trillion.
Phase Three will consist of Ulujami-Tanah Abang (8.7 KM) for Rp4.25 trillion, while Phase Four for Pasar Minggu-Casablanca (9.15 KM) for Rp5.71 trillion.